Sunil Hitech Engineers has secured Letter of Award (LoA) from National Highways Authority of India (NHAI) to construct and widen the existing 2-lane Bodhre to Dhule road section of NH-211 to four/six lane configuration in the State of Maharashtra for a bid project cost of Rs 982 crore on Hybrid annuity Model (HAM). The construction of the 67.2 km road also include 2 new ROBs, 6 underpasses, 4 major bridges, 26 minor bridges and 2 new bypasses.
The company will be signing the concession agreement soon. The construction period is 2.5 years.
Sunil Hitech Engineers is a well established player in EPC and Construction of Road & Bridges, Building works of institutions, hospitals and housing projects, cross country pipeline, civil & mechanical works of power and steel plants, cooling towers, chimneys, etc. and also in renewable energy sector.