NHPC’s Unit no 1 of Chamera HE Project to commence commercial operation

Date: 02-07-2012

NHPC’s Unit no 1 of Chamera HE Project (Stage III) is declared under commercial operation with effect from July 04, 2012. This is consequent upon successful trial run and demonstration of peaking capability corresponding to its installed capacity of 77 MW.

The Unit no 2 and 3 of the project are already under commercial operation with effect from June 30, 2012. Besides, the peaking capability corresponding to installed capacity 3 X 77 (231 MW) of the station is demonstrated and commercial operation of the generating station as a whole is also declared with effect from July 04, 2012.

NHPC is engaged in the planning, development and implementation of an integrated and efficient network of hydroelectric projects in India. It executes all aspects of the development of hydroelectric projects, from concept to commissioning.