-3.20 (-1.24%) Power Grid Corporation of India has received investment approvals for Scheme to relieve high loading of WR-NR Inter Regional Corridor (400 kV Bhinmal-Zerda line) at an estimated cost of Rs 200.58 crore scheduled to be commissioned by May 2024; Transmission system for Augmentation of ISTS for interconnection of HVPNL Transmission Schemes at an estimated cost of Rs 107.77 crore scheduled to be commissioned progressively from February 2024 to July 2024; Implementation of Western Region Expansion Scheme-XXV (WRES-XXV) at an estimated cost of Rs 385.84 crore scheduled to be commissioned by November 2023; and Implementation of North Eastern Region Expansion Scheme-XX (NERES-XX) at an estimated cost of Rs 109.38 crore scheduled to be commissioned by November 2024.
The 'Committee of Directors on Investment on Projects' of POWERGRID in its meeting held on February 24, 2023 has accorded approvals for the same.
Power Grid Corporation of India is an Indian state-owned electric utilities company headquartered in Gurgaon, India.