-40.85 (-1.07%) Larsen & Toubro (L&T) has reportedly secured contract from Saudi Aramco to build facilities including a gas processing plant for its Midyan gas field. The project comprised building two pipelines of 98 km length to deliver gas and hydrocarbon liquids to a power plant near (the western city of) Duba.
The company will construct a plant with a processing capacity of 75 million standard cubic feet per day (scfd) of non-associated gas and 4,500 barrels of condensate per day. The project is expected to be completed in mid-2016.