Hindustan Petroleum Corp Ltd (HPCL) plans to invest Rs13,000 crore to almost double the capacity of its Vizag oil refinery in Andhra Pradesh to 15 million tonnes a year by 2013-14. The decision to expand the Vizag refinery follows steel tycoon Lakshmi Mittal group and French oil firm Total SA walking out of a proposed USD 4 billion project to build a 15 million tonnes per annum refinery and a 2.5 million tonnes per annum petrochemicals plant near HPCL's 8.3 million tonnes per annum refinery at Visakhapatnam.
HPCL does not intend to bring a partner onboard for the refinery expansion. It may add a new 180,000 barrels per day (9 million tonnes per annum) crude distillation unit (CDU) and scrap the old 36,000 bpd (1.8 million tonnes per annum) unit at the Vizag refinery.
HPCL is also looking at investing Rs30,000 crore to set up an 18 million tonnes a year refinery. The new refinery, to be set up in Maharashtra, was conceptualised to make up for space constraints at HPCL's existing Mumbai Refinery.