BHEL assures timely supply of equipment to AP Genco

07 Sep 2012 Evaluate

BHEL, the power equipment maker has guaranteed Generation Corporation of Andhra Pradesh (AP Genco) of timely supply of turbines for 2,800 MW of expansion projects. AP Genco is executing several projects in the State and aims to complete the projects on time due to demand-supply mismatch in the State which worsened due to shortage of gas supply from KG Basin.

The new projects includes Kakatiya thermal power of 600 MW with the planned date of commissioning December 2012, Krishnapatnam thermal power 2x800 MW with unit I in June next year and unit II in December next year and Rayalaseema thermal power station of 600 MW to be commissioned by August 2014.