Suzlon Energy has informed that Suzlon has secured a new order of 252 MW with CLP India. The detailed press release for the same is attached herewith. This is also informed that the Company has completed the formalities for termination of an order of 500MW with Torrent Power. The Company’s order book already excludes the 500 MW cancelled order of Torrent Power, which was removed from the order book since Q3 FY20 on account of teething troubles of land, power evacuation and other constraints.

The above information is a part of company’s filings submitted to BSE.