Power Grid Corporation Of India informs about board decision

19 Feb 2024 Evaluate
Power Grid Corporation Of India has informed that Powergrid, in its Board of Directors and 'Committee of Directors on Investment on Projects' in their respective meetings held on 18th February, 2024, have accorded Investment approvals for the following projects: Board of Directors-‘Implementation of Unified Load Dispatch and Communication (ULDC) Phase-III (SCADA/EMS Upgradation Project -Northern Region SLDCs)’ at an estimated cost of Rs. 514.66 crore with commissioning schedule of 15.11.2025; Committee of Directors on Investment on Projects-‘Augmentation of 765/400 kV, 1500 MVA transformer (4th) at Bhiwani S/s (Delinked from Transmission System for evacuation of power from RE parks in Leh (5GW Leh-Kaithal Transmission corridor))’, at an estimated cost of Rs. 141.09 crore, scheduled to be commissioned in a timeframe of 18 months from the date of issue of MoP OM, by 05.05.2025.

The above information is a part of company’s filings submitted to BSE.