Bigbloc Construction to temporary shutdown Umargam plant for 45-60 days

15 May 2024 Evaluate

Bigbloc Construction is all set for the scheduled shutdown of its Umargam plant from May 18, 2024, for 45-60 days. This temporary closure is essential to facilitate the implementation of automation, upgrades to Cutting and Packing Lines, and various other enhancements to its production processes.

There will not be any impact on sales since this is a pre-planned shut down and the company will supply from its other plants. Anticipated outcomes from these improvements include reduced wastage and raw material costs, increase in operational efficiency as well as a decrease in manpower requirements. The company remains committed to enhancing its operational capabilities and ensuring sustainable growth for the benefit of all stakeholders.

Bigbloc Construction is engaged in the business of manufacturing of building blocks and AAC Bricks.


Bigbloc Construction Share Price

73.11 -1.84 (-2.45%)
02-Jan-2026 16:59 View Price Chart
Peers
Company Name CMP
Ultratech Cement 11895.45
Ambuja Cement 565.20
ACC 1748.85
Shree Cement 27026.65
Dalmia Bharat 2146.00
View more..
Register Now to get our Free Newsletter & much more!

© 2026 The Alchemists Ark Pvt. Ltd. All rights reserved. MoneyWorks4Me ® is a registered trademark of The Alchemists Ark Pvt. Ltd.

×