CESC’s arm synchronizes 300 MW Thermal Power Unit at Haldia

14 Jan 2015 Evaluate

CESC’s 100% subsidiary - Haldia Energy has synchronized the first 300 MW Thermal Power Unit of 2 x 300MW project located at Haldia in West Bengal. The company has also generated power at the station which is now flowing to Kolkata through a 84km long transmission line.

CESC is engaged in power generation and distribution in state of West Bengal. CESC is a fully integrated power utility with its operation spanning the entire value chain: right from mining coal, generating power, distribution of power.

CESC Share Price

167.60 -6.40 (-3.68%)
08-Dec-2025 14:52 View Price Chart
Peers
Company Name CMP
NTPC 319.25
Tata Power 374.25
Adani Power 139.50
Power Grid Corp 265.60
Torrent Power 1253.45
View more..
Register Now to get our Free Newsletter & much more!

© 2025 The Alchemists Ark Pvt. Ltd. All rights reserved. MoneyWorks4Me ® is a registered trademark of The Alchemists Ark Pvt. Ltd.

×