CESC’s arm synchronizes 300 MW Thermal Power Unit at Haldia

14 Jan 2015 Evaluate

CESC’s 100% subsidiary - Haldia Energy has synchronized the first 300 MW Thermal Power Unit of 2 x 300MW project located at Haldia in West Bengal. The company has also generated power at the station which is now flowing to Kolkata through a 84km long transmission line.

CESC is engaged in power generation and distribution in state of West Bengal. CESC is a fully integrated power utility with its operation spanning the entire value chain: right from mining coal, generating power, distribution of power.