Sadbhav Infrastructure commences toll collection at Rajsamand- Bhilwara section

10 Jun 2016 Evaluate

Sadbhav Infrastructure Project’s wholly-owned subsidiary - Bhilwara-Rajsamand Tollway (BRTPL) has received Provisional Completion Certificate for 86 km. out of total 87.25 km. on June 04, 2016 and accordingly toll collection has been started on the Project from June 09, 2016.

The completed Project Length of 86.000 Km involved construction of 1 ROB at Kuanwarian, 1 Major Bridge in Potlan Bypass across Chandra Bhaga River, 6.92 Km long Pur Bypass, 3.60 Km Karoi Bypass, 2.55 Km Potlan Bypass & 2.45 Km Kuanwarian Bypass. The scope of work also included the construction of 15 No’s Minor Bridges, 3 No Vehicular Underpasses, 8 No Pedestrian Underpasses, 15.2 Kms (2 x 7.6 Kms) Slip Road and 2 No Toll Plazas among other Works.

With the above, out of total portfolio of 11 Projects, 10 projects (including MBCPNL which is partially operational) are operational and 1 project is in advanced stage of construction.


Sadbhav Infra. Proj Share Price

3.36 -0.13 (-3.72%)
23-Jan-2026 15:40 View Price Chart
Peers
Company Name CMP
Larsen & Toubro 3745.05
Rail Vikas Nigam 325.35
NCC 142.35
KEC International 635.65
Kalpataru Projects 1107.80
View more..
Register Now to get our Free Newsletter & much more!

© 2026 The Alchemists Ark Pvt. Ltd. All rights reserved. MoneyWorks4Me ® is a registered trademark of The Alchemists Ark Pvt. Ltd.

×