IL&FS Engineering and Construction Company has received letter from Paschimanhal Vidyut Vitran Nigam, Meerut (PVVNL) for termination of contract for rural electrification works (RE works) of villages of Moradabad district.

The reason given for the termination is that the company has completed work in 929 villages against scope of 1028 villages about 89% of awarded works. Client terminated the contract due to slow progress / stoppage of balance works. Whereas, the company stopped work due to payments held up by PVVNL.

The impact to the company due to the termination of the contract is Rs 46 crore bank guarantees held by client and unpaid bills of Rs 57 crore.

As per the company, the termination is illegal. Accordingly, the company is in the process of initiating legal / contractual actions against the said termination to protect its rights and entitlements in terms of the provisions of the Contract.

IL&FS Engg. & Const. Share Price

27.00 -0.50 (-1.82%)
18-Dec-2025 16:59 View Price Chart
Peers
Company Name CMP
Larsen & Toubro 4032.00
Rail Vikas Nigam 305.70
NCC 153.05
KEC International 700.55
Kalpataru Projects 1121.20
View more..
Register Now to get our Free Newsletter & much more!

© 2025 The Alchemists Ark Pvt. Ltd. All rights reserved. MoneyWorks4Me ® is a registered trademark of The Alchemists Ark Pvt. Ltd.

×