L&T commissions 360 MW Bheramara combined cycle power plant in Bangladesh

09 Jan 2018 Evaluate

Larsen & Toubro (L&T) has successfully commissioned and handed over the state-of-the-art 360 MW Bheramara Combined Cycle Power Plant Development Project to North West Power Generation Company (NWPGCL), a fully owned subsidiary of Bangladesh Power Development Board (BPDB), on January 5, 2018. After performance testing, the plant capacity has been declared as 410 MW by the customer. This power plant is based in Bheramara of Kushtia District in the western sector of Bangladesh, which is approximately 250 km from Kolkata, India.

The company’s scope of work included design, engineering, supply, installation and commissioning of the complete power plant on a back-to-back turnkey basis for Marubeni Corporation of Japan, with Gas Turbines, Steam Turbine and Generators from Mitsubishi Hitachi Power Systems, Japan.

This project has been executed by the Gas Based Power Projects Business Unit of L&T, based out of Vadodara. L&T’s well-established strengths in design, engineering and construction, combined with robust quality and safety standards and on-time delivery, are vital contributors to its success in the power sector.

Larsen & Toubro Share Price

4052.80 -6.35 (-0.16%)
24-Dec-2025 16:59 View Price Chart
Peers
Company Name CMP
Larsen & Toubro 4052.80
Rail Vikas Nigam 345.70
NCC 161.40
KEC International 737.85
Kalpataru Projects 1199.70
View more..
Register Now to get our Free Newsletter & much more!

© 2025 The Alchemists Ark Pvt. Ltd. All rights reserved. MoneyWorks4Me ® is a registered trademark of The Alchemists Ark Pvt. Ltd.

×