BGR Energy Systems has secured two orders for an aggregate value of Rs 431 crore from Nuclear Power Corporation of India (NPCIL).
The first order is for the design & detailed engineering, manufacture, procurement, supply, etc. of 400KV & 230KV Switchyards and BoP electrical areas for Kudankulam Nuclear Power projects - 3 & 4 for a total value of Rs 344.83 crore.
The second order is for loading/unloading, transportation & handling at site, storage, civil works, etc., of 400KV & 230KV Switchyards and BoP electrical areas for Kudankulam Nuclear Power projects - 3 & 4 for Rs 86.21 crore. The contract completion period is 60 months.
BGR Energy Systems is a holding company. The company is engaged in construction and maintenance of power plants.