Dilip Buildcon has received a Provisional Completion Certificate for the project of four laning of Yavatmal to Wardha (Package-III) section of NH-361 from Km 400.575 to Km 465.500 (design length 64.925 Km) under NHDP Phase -IV on Hybrid Annuity mode in the state of Maharashtra.
The Provisional Completion Certificate has been issued by the authority and has declared the project fit for entry into operation as on August 02, 2019 and consequently, the company is entitled to maximum bonus of Rs 38.29 crore in lieu of earlier completion (367 days prior to the schedule completion date) of the said Project.
Dilip Buildcon’s core business is undertaking construction projects across India in the roads and irrigation sectors. They specialize in constructing state and national highways, city roads, culverts and bridges.