NLC India completes trial operation of Unit 2 of Neyveli New Thermal Power Project

05 Feb 2021 Evaluate

NLC India has successfully completed 72 hours of continuous trial operation of 500 MW of Second Unit (Unit 2) of 2 x 500 MW pit head lignite fired Neyveli New Thermal Power Project (NNTPP) at its rated capacity on February 3, 2021. The 500 MW Capacity Lignite fired Boilers of NNTPP are first of its kind in India. The First Unit (Unit 1) was already commissioned and with this, the Power Plant will be fully commissioned.

The formal clearance from Southern Regional Load Despatch Centre (SRLDC) is in process for Declaration of Commercial Operation of the Unit. The Steam Generator and Turbine Generator Packages are executed by BHEL. With this commissioning of Unit 2, the total installed Power Generation capacity of NLC India group increased to 6061.06 MW. The states of Tamil Nadu, Kerala, Karnataka, Andhra Pradesh, Telangana and Puducherry are beneficiaries of this station.

NLC India is engaged in the business of lignite mining and power generation.


Neyveli Lignite Share Price

257.60 1.75 (0.68%)
13-Jan-2026 12:09 View Price Chart
Peers
Company Name CMP
NTPC 337.00
Tata Power 368.10
Adani Power 142.80
Power Grid Corp 258.20
Torrent Power 1337.50
View more..
Register Now to get our Free Newsletter & much more!

© 2026 The Alchemists Ark Pvt. Ltd. All rights reserved. MoneyWorks4Me ® is a registered trademark of The Alchemists Ark Pvt. Ltd.

×