SJVN inaugurates works of second unit of 1320 MW Buxar Thermal Power Plant

24 Nov 2021 Evaluate

SJVN has inaugurated the works of Second Unit of (2 X 660) 1320 MW Buxar Thermal Power Plant. The project consists of two units and that more than 50% works related to First unit have already been completed. The 1320 MW Buxar Thermal Power Plant with Ultra Super Critical Technology is being developed by SJVN Thermal (a fully owned subsidiary of SJVN).

SJVN is engaged in hydroelectric power generation originally established as a joint venture between the government and the state government of Himachal Pradesh to develop and operate the Nathpa Jhakri Hydro Power Station (NJHPS).