SJVN has inaugurated the upstream cofferdam of 66 MW Dhaulasidh Hydro Electric Project at Hamirpur in Himachal Pradesh. The cofferdam has been completed four months ahead of the schedule, in a record time of 4 months 10 days. This marks the completion of river diversion works, paving way for full-scale excavation works of the dam foundation, which is already in progress.
The project is a run-of-river scheme on river Beas. It will generate 304 million units of energy on completion. The project is contributing to the overall development of the area with community asset creation, infrastructure development and generation of direct and indirect employment.
SJVN’s principal business activity is electricity generation. The company is also engaged in the business of providing consultancy.