SJVN has entered into an agreement for the construction of a 220 KV D/C (direct current) single zebra transmission line for 210 MW Luhri Hydro Electric Project Stage-1 with Kalpataru Power Transmission.
This hydroelectric project which is spread over Shimla, Mandi and Kullu districts of Himachal Pradesh will be connected with 220/400 KV GIS pooling at Nanj in Mandi district via ISTS network for power transmission. The agreement envisages an expenditure of Rs 71.18 crore and it includes end-to-end delivery of commissioned transmission line by August 2024.
SJVN’s principal business activity is electricity generation. The company is also engaged in the business of providing consultancy.