Kalpataru Power Transmission and SJVN have entered into an agreement where the company will construct a 220 KV direct current single zebra transmission line for 210 MW Luhri Hydro Electric Project Stage-1 of SJVN.
This hydroelectric project which is spread over Shimla, Mandi and Kullu districts of Himachal Pradesh will be connected with 220/400 KV GIS pooling at Nanj in Mandi district via ISTS network for power transmission. The agreement envisages an expenditure of Rs 71.18 crore and it includes end-to-end delivery of commissioned transmission line by August 2024.
Kalpataru Power Transmission is one of the largest and fastest growing specialized EPC companies in India engaged in power transmission & distribution, oil & gas pipeline, railways, infrastructure development, civil contracting and warehousing & logistics business with a strong international presence in power transmission & distribution.