Knr Constructions has informed that provisional Certificate of Completion for ‘Four laning of Oddanchatram to Madathukulam section of NH-209 (new NH-83) from Design Km 29.000 to Km 74.380 under Bharatmala Pariyojana Phase I under the category of Residual Works of NHDP on Hybrid Annuity Mode in the State of Tamilnadu’ effective from 02nd September 2022 was received by KNR Palani Infra, a Wholly Owned Subsidiary of the Company and the Project was completed 185 days ahead with the Revised Scheduled Completion Date with an entitlement of Bonus.

The above information is a part of company’s filings submitted to BSE.