KP Energy has successfully commissioned 29.4MW (Phase-II) ISTS connected wind power project comprising 14 numbers of WTGs of 2.1MW each at Sidhpur Site in Devbhoomi Dwarka.
This Phase-II commissioning is a part of the 250.8MW ISTS connected wind power project capacity awarded to Apraava by Solar Energy Corporation of India (SECI) under Tranche-VIII bidding. With the present Phase-II commissioning the net cumulative capacity commissioned stands at 81.9MW (i.e. 52.50MW + 29.4MW) against the awarded capacity 250.8MW.
KP Energy is engaged in operating solar and wind energy projects in India.