MoneyWorks4Me

Pursuant to Regulation 30 of SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015, K.P. Energy has announced that KP Energy has successfully completed the development activities and charged the 140MW power evacuation system for wind-solar hybrid power project at Fulsar site in Taluka Talaja, District Bhavnagar, Gujarat. The power evacuation system comprised of 140MW hybrid Pooling Sub-station, 66kv Extra High Voltage Line and the 66kv bay at the Shelavadar Grid Sub-station. The 140MW power evacuation system is developed by KP Energy for ABREL EPC (Aditya Birla Company) at Fulsar site for wind solar hybrid power project under the Gujarat Wind-Solar Hybrid Power policy, 2018.

The above information is a part of company’s filings submitted to BSE.


Peers
Company Name CMP
Larsen & Toubro 3860.00
Kalpataru Projects 1447.10
NCC 137.00
Rail Vikas Nigam 210.30
KEC International 402.50
View more..