SJVN has commissioned both the units of 60 MW Naitwar Mori Hydro Power Station (NMHPS) on River Tons, a major tributary of River Yamuna in Uttarkashi district of Uttarakhand. Both the units are now generating commercially after going through rigorous testing and successful synchronization with the national grid. With this achievement, the installed generation capacity of the company now stands at 2152 MW.

The project will generate 265.5 million units of electricity annually. The power will be evacuated through the 37 km long 220 KV Transmission Line from Bainol to Snail which has also been constructed by the Company. The project consists of a diversion structure which is 18.5 meters high and 50 meters long at the top. From this, water has been diverted into 4.33- kilometre-long Head Race Tunnel with a diameter of 5.6 meters. The power house, which is an underground structure, consists of two generating units of 30 MW each. The project has been designed for the discharge of 75.3 cubic meter per second, while the head is 90.76 meters.

After commissioning of the project, 12% free electricity will be supplied to the state of Uttarakhand as royalty. In addition, each Project Associated Family will be provided with an amount equivalent to the cost of 100 Units of electricity per month for ten years.

SJVN’s principal business activity is electricity generation. The company is also engaged in the business of providing consultancy.


SJVN Share Price

71.31 -2.74 (-3.70%)
08-Dec-2025 16:59 View Price Chart
Peers
Company Name CMP
NTPC 319.45
Tata Power 374.30
Adani Power 139.05
Power Grid Corp 265.20
Torrent Power 1254.10
View more..
Register Now to get our Free Newsletter & much more!

© 2025 The Alchemists Ark Pvt. Ltd. All rights reserved. MoneyWorks4Me ® is a registered trademark of The Alchemists Ark Pvt. Ltd.

×