HG Infra Engineering has been declared as L-1 bidder by East Central Railway for the project ‘Construction of double line track (3rd & 4th line) formation including earth work, blanketing, minor bridges, major bridges, electrification works and other miscellaneous works for 32.5 T axle load including Electrical TRD (2x25 KV) in Gaya-Son Nagar section (in between DFCC CH:225.300 (IR CH:475.200) to DFCC CH:292.175 (IR CH:542.075)) in DDU Division of East Central Railway in the state of Bihar. The company's bid project cost is Rs 709.11 crore and the construction period is 36 months.
HG Infra Engineering is an infrastructure construction, development and management company with extensive experience in its focus area of road projects, including highways, bridges and flyovers.