Rail Vikas Nigam has received Letter of Acceptance (LoA) from Central Railway for Design, Supply, Erection, Testing & Commissioning of 132/55 KV Traction Substation, Sectioning post (SPs) and Sub sectioning post (SSPs) in 2 x 25 KV Traction System (Scott Connected Transformer) of Bhusaval- Khandwa Sections of Central Railway, to meet 3000 MT loading target on EPC mode. Cost of work is Rs 135.66 crore including applicable taxes. The said order is expected to completed in 24 months.
Rail Vikas Nigam functions as an extended arm of the Ministry of Railways.