NTPC Green Energy informs about declaration of commercial operation

01 Mar 2025 Evaluate

In line with disclosure requirements under Regulation 30 of SEBI (Listing Obligations and Disclosure Requirements) Regulations 2015, NTPC Green Energy has informed that, Consequent upon successful commissioning, fourth & last part capacity of 18.32 MW out of 300 MW Shambu ki Burj-2 (Kolayat) Solar PV Project at Bikaner, Rajasthan, is declared on Commercial Operation with effect from 00:00 Hrs. of 01.03.2025. The first part capacity of 150 MW, second part capacity of 98.78 MW and third part capacity of 32.90 has already been declared on commercial operation with effect from 00:00 Hrs. of 29.09.2022, 23:00 Hrs. of 30.09.2024 and 00:00 Hrs of 31.10.2024 respectively.

The above information is a part of company’s filings submitted to BSE.