NTPC informs about updates

12 Jun 2025 Evaluate
In line with the Corporate Disclosure requirements, NTPC has informed that based on achievement of approved norms and due approvals, Unit-3 of 660 MW capacity of North Karanpura Super Thermal Power Project, (3 x 660 MW) has successfully completed trial operation and consequently included in the installed capacity of the company. With this, the total installed capacity of NTPC on standalone and group basis has become 60266 MW and 81368 MW respectively.

The above information is a part of company’s filings submitted to BSE.