NTPC informs about updates

17 Dec 2025 Evaluate

NTPC has informed that consequent upon successful commissioning, 78 MW out of 245 MW capacity at Plot-1 of NTPC's Nokh Solar PV Project (3x245MW), Rajasthan, is declared on Commercial Operation with effective from 00:00 Hrs. of 18.12.2025. With this, the total installed and commercial capacity of NTPC on standalone and group basis will now become 60,783 MW & 85,259 MW respectively.

The above information is a part of company’s filings submitted to BSE.