MoneyWorks4Me

Power Grid Corporation gets nod for cold spare transformers, reactors procurement

21 Jan 2026 Evaluate

Power Grid Corporation of India has received approval from Committee of Directors on Investment on Projects for implementation of ‘Procurement of cold spare Transformers & Reactors approved in 51st WRPC’, at an estimated cost of Rs 401.88 crore, scheduled to be implemented within 30 months from the date of Investment Approval. 

The company has received approval for implementation of ‘Procurement of cold spare Transformers & Reactors approved in 28th NERPC’, at an estimated cost of Rs 166.33 crore, scheduled to be implemented within 30 months from the date of Investment Approval.

Further, the company has also received approval for implementation of ‘Procurement of cold spare Transformers & Reactors approved in 53rd SRPC’, at an estimated cost of Rs 345.78 crore, scheduled to be implemented within 30 months from the date of Investment Approval.

The committee of Directors on Investment on Projects of Power Grid Corporation, in its meeting held on January 20, 2026, has considered and approved the same.

Power Grid Corporation of India is an Indian state-owned electric utilities company headquartered in Gurgaon, India.

Peers
Company Name CMP
NTPC 330.00
Tata Power 363.30
Adani Power 202.00
Power Grid Corpn. 263.50
Adani Energy Solut. 1346.95
View more..