Pursuant to Regulation 30 read with Part B of Schedule III of the SEBI Listing Regulations, 2015, CESC has informed that Deshraj Solar Energy, a step-down subsidiary of the Company, has declared the Commercial Operation Date (COD) of 147 MW out of its 150 MW Solar Power Project located at Village Karnisar Bhatiyan, District Bikaner, Rajasthan, connected at ISTS Bikaner-III (PGCIL) substation, with effect from November 21, 2026, following the successful trial run certified by Grid Controller of India (Northern Regional Load Despatch Centre) vide certificate dated November 19, 2026. The balance capacity of 3 MW is expected to be commissioned by January 31, 2027.
The above information is a part of company’s filings submitted to BSE.