Bharat Heavy Electricals (BHEL) has successfully completed renovation and modernization of 110 MW Unit-7 at Harduaganj Thermal Power Station (TPS) Plant of Uttar Pradesh Rajya Vidyut Utpadan Nigam (UPRVUNL). After successfully running for over 30 years, this unit, originally supplied and commissioned by BHEL, was undertaken for Renovation & Modernization (R&M).

Following the R&M, not only was the working life of the machine extended by another 15-20 years, the capacity was also uprated to 120 MW from its original capacity of 110 MW. With this, the company has once again showcased its inherent strength of being fully geared for R&M and uprating of old thermal power plants through in-house state-of-the-art technology, engineering capabilities and by incorporating the latest products/systems in renovated units.

Significantly, this is the eighth such unit successfully renovated, modernised and uprated by the company from its original rating of 110 MW to 120 MW. The achievement of full load of this unit comes close on the heels of the successful commissioning of Rihand Hydro Unit-3 (50 MW) of Uttar Pradesh Jal Vidyut Nigam (UPJVNL), following R&M.

Notably, the unit was more than 50 years old and supplied by M/s English Electric in 1962. In order to bridge the gap between demand and supply, especially in the context of limited financial resources available and difficulty in land acquisition and environment clearance it has become imperative for the country to look for other options for cheaper and faster generating capacity enhancement.

BHEL Share Price

262.85 2.45 (0.94%)
30-Jan-2026 16:59 View Price Chart
Peers
Company Name CMP
BHEL 262.85
Thermax 2881.95
Kirloskar Oil Eng 1173.20
Skipper 361.20
GMM Pfaudler 974.05
View more..
Register Now to get our Free Newsletter & much more!

© 2026 The Alchemists Ark Pvt. Ltd. All rights reserved. MoneyWorks4Me ® is a registered trademark of The Alchemists Ark Pvt. Ltd.

×