Nava Bharat Ventures’ Turbine plant at Paloncha to restart its operations by October 25

12 Oct 2015 Evaluate

Nava Bharat Ventures’ 50 MW Turbine power plant at Paloncha in state of Telangana after renovation and overhaul, is expected to restart its operations by October 25, 2015 with improved turbine heat rate and efficiency of the unit. The 50 MW Turbine was taken up for renovation and overhaul with effect from August 24, 2015 as scheduled.

Initially, it was expected to complete the renovation and restart the operations by October 15, 2015. The renovation works are being continued and are now expected to be completed by October 24, 2015 due to increased volume of technical work.

Nava Bharat Ventures (NBV) operates in the business verticals of power generation, mining, ferro alloys and agri-business with multi-national operations spread over India, South East Asia and Africa.


Nava Share Price

526.45 -2.90 (-0.55%)
05-Dec-2025 16:59 View Price Chart
Peers
Company Name CMP
NTPC 323.40
Tata Power 384.30
Adani Power 143.75
Power Grid Corp 269.75
Torrent Power 1284.50
View more..
Register Now to get our Free Newsletter & much more!

© 2025 The Alchemists Ark Pvt. Ltd. All rights reserved. MoneyWorks4Me ® is a registered trademark of The Alchemists Ark Pvt. Ltd.

×