State-owned BHEL has bagged Rs 5,450 crore order from a Bajaj group company for supplying power equipment for setting up the 1,980 MW thermal power project at Lalitpur in Uttar Pradesh. The company has bagged the main plant package contract for three coal-fired thermal units of 660 MW each with supercritical parameter.

BHEL is already executing five major contracts for supply of main plant equipment with supercritical parameters for various power projects in the country. BHEL is also executing a contract for supply of supercritical Steam Generators to APGenco's 2x800 MW Krishnapatnam Thermal Power Project, which is in an advanced stage of completion. BHEL has established the capability to deliver 15,000 MW of power equipment per annum and further augmentation to 20,000 MW per annum is underway.crackcrack