Bharat Heavy Electricals Ltd, Tiruchi, has chalked out a major capacity expansion programme in the next two years at an investment of Rs 600 crore.This includes the Phase III expansion for a high pressure boiler plant at the existing unit and the Thirumayam unit, which will cater tothe demand from petrochemical industries and nuclear equipment manufacturers.

The Rs 293-crore Thirumayam unit, which will be operational by the end of this year, will have a shop area of about 39,000 sq m. The unit is all set to achieve a record turnover of Rs 12,765 crore, and has set a turnover growth of over 30 per cent for 2011-12.The Tiruchi complex, which contributes 30 per cent of the company's overall turnover and 40 per cent of the group's profit, has outstanding orders worth Rs 38,600 crore till November 2010.

The group has realised the capability to deliver 15,000 MW per annum in March 2010, and the capacity expansion programme is underway to reach 20,000 MW by 2012.crackcrack

Related Bharat Heavy Electricals Ltd. Links:

BHEL Share Price

54.15 0.35 (0.65%) Nov 15, 18:01
1 Year Price Chart
Peers
Company Name CMP
BHEL 54.15
Bharat Electronics 111.20
Thermax 1050.50
ISGEC Heavy Engg. 397.60
BEML 952.55
View more..
Sensex vs BHEL
Puchho Befikar
SEBI Registered: Investment Adviser - INA000013323
Research Analyst - INH000000719

Callback

8055769463

8055769463