MoneyWorks4Me

Bharat Heavy Electricals (BHEL) has successfully commissioned another 270 MW thermal unit at Rattanlndia Nasik Power's 5x270 MW thermal power project, located at Sinnar in Nasik District of Maharashtra.  This is the fourth unit to be commissioned at this project. Significantly, the milestone has been achieved within 35 days of commissioning of the third unit.

So far, BHEL has successfully commissioned 14 sets of 270 MW rating in the country, including 9 sets for the Rattanlndia group. In addition to four units at Nasik, BHEL has earlier commissioned 5 sets of 270 MW each at Amravati, for Rattanlndia. The fifth unit at the Nasik project is also in advanced stages of completion.

BHEL's scope of work in the project envisaged design, engineering, manufacture, supply, erection and commissioning of Steam Turbines, Generators, Boilers, associated Auxiliaries and Electricals, besides state-of-the-art Controls & Instrumentation (C&I) and Electrostatic Precipitators (ESPs).  The equipment for the project was supplied by various manufacturing units of BHEL located at Trichy, Ranipet, Hyderabad, Bengaluru, Bhopal and Haridwar while the construction work was carried out by BHEL's Power Sector - Western Region.

Peers
Company Name CMP
Bharat Heavy Elect. 434.00
Thermax 3550.45
Kirloskar Industries 3695.90
Skipper 565.95
INDO-MIM 1057.85
View more..