In line with its objective of achieving excellence in project execution, Bharat Heavy Electricals (BHEL) has implemented an innovative boiler cleaning process for coal-fired thermal units, at NTPC’s 3x660 MW North Karanpura Super Thermal Power Project, being executed by BHEL on EPC basis.

The boiler commissioning cycle will reduce from 100 days to 80 days by successfully completing the main ‘Boiler Acid cleaning’ without its light-up, by using an Auxiliary Boiler. This innovative method is a major change in the commissioning process followed so far and will aid in early synchronisation of the unit.

BHEL is India’s largest engineering and manufacturing company of its kind. It is a power plant equipment manufacturer and operates as an engineering and manufacturing company.

BHEL Share Price

258.05 6.10 (2.42%)
02-Feb-2026 16:59 View Price Chart
Peers
Company Name CMP
BHEL 258.05
Thermax 2829.90
Kirloskar Oil Eng 1151.20
Skipper 355.60
GMM Pfaudler 971.65
View more..
Register Now to get our Free Newsletter & much more!

© 2026 The Alchemists Ark Pvt. Ltd. All rights reserved. MoneyWorks4Me ® is a registered trademark of The Alchemists Ark Pvt. Ltd.

×